INVESTMENT PROCEDURE
VIGLACERA PROVIDES ONE-STOP SERVICE
to support and guide businesses throughout the investment process
Sign the Principle Agreement for land sublease
Apply for Investment Registration Certificate
Apply for Enterprise Registration Certificate, Tax Code, and Seal
Sign the official land sublease and handover the land
Agree on Connection points (water supply, wastewater drainage, electricity connection, and gate location)
Submit the construction designs for approval following the basic design stage
Submit the Fire Prevention and Fighting Plan for approval
Submit the Environmental Impact Assessment for approval
Apply for Construction Permit
Construct the factory, install machinery and equipment
Register for Land Use Rights Certificate (independent step)
* Step 4, 5, 6 can be performed simultaneously * Step 7, 8 can be performed simultaneously * Step 11 can be performed after Step 4